MT. PLEASANT—The Mt. Pleasant City Council discussed a reported $73,587 shortfall associated with the city’s Veterans Memorial project at a council meeting.
Finance director David Oxman said the city needed to close out the project’s construction-phase, which has been tracked in an account known as a “Local Building Authority,” and determine how to cover the remaining financial obligations.
Council members reviewed earlier discussions involving recreation, arts and parks (RAP) tax funds and a separate city contribution.
According to the discussion, the RAP tax committee had previously recommended $70,000 for the memorial. The council initially authorized $35,000, leaving the remaining RAP tax amount available for later consideration.
Members also discussed a $30,000 city contribution, approved early in deliberations about the memorial. However, they were uncertain whether that amount had actually been transferred to the project.
"I need to double-check the $30,000," Oxman said.
Another possibility that was discussed was using an additional $35,000 in RAP tax funds and covering the rest through city capital funds.
Council members acknowledged that additional expenses could arise, including costs associated with correcting or reprinting names displayed at the memorial.
During the discussion council members mentioned the substantial donations of labor, materials and other contributions that helped complete the project.
Officials noted that those donations were not fully reflected in the project’s recorded expenditures.
Rather than approve additional funding, the council agreed to wait until the financial records could be reconciled and the remaining expenses better established.